Installation

Heat Pump Installation: What to Expect

A day-by-day breakdown of the heat pump installation process from survey to completion.

Wondering what actually happens during a heat pump installation? Here's the complete process explained step by step.

Timeline Overview

Initial survey:1-2 hours
Quote provided:3-7 days later
Grant application:48 hours approval
Installation:2-3 days for air source, 5-10 days for ground source
Commissioning:Half day
Total time (booking to completion):4-12 weeks typical

Stage 1: Initial Survey (Week 1)

An MCS certified surveyor visits your home to assess suitability. This takes 1-2 hours and includes:

  • Heat loss calculation: Room-by-room measurement to determine required heat pump size
  • Property inspection: Insulation levels, radiator types and sizes, existing heating system
  • Outdoor space assessment: Location for outdoor unit, distance to indoor unit, drainage
  • Electrical check: Consumer unit capacity, cable runs required
  • Hot water needs: Current cylinder or need for new one, sizing requirements

🔍 What the surveyor will tell you:

  • • Whether your home is suitable (most are)
  • • Recommended heat pump size (kW rating)
  • • Any prep work needed (radiator upgrades, cylinder replacement)
  • • Estimated installation timeline

Stage 2: Quote & Grant Application (Week 1-2)

Within a week, you'll receive a detailed quote showing:

  • Full installation cost breakdown
  • Less £7,500 BUS grant
  • Your final payment amount
  • Equipment specifications (brand, model, warranty)
  • Payment schedule (typically deposit, then balance on completion)

Once you accept, the installer applies for your BUS grant. Ofgem typically approves within 48 hours, issuing a redemption code valid for 3 months.

Stage 3: Pre-Installation Prep (Week 2-4)

Before installation day, you may need:

Radiator upgrades (if required):

Some older radiators are too small for heat pump flow temperatures. Installer will replace undersized radiators (typically 2-4 per home). This adds 1 day to timeline and £500-1,500 to cost.

Hot water cylinder replacement:

If you have a combi boiler (no cylinder), you'll need a new unvented cylinder installed. Takes half a day, typically £800-1,200 included in quote.

Electrical work:

Heat pump needs dedicated circuit from consumer unit. Electrician runs cable to outdoor unit location. Usually done on Day 1 of installation.

Stage 4: Installation Days (Air Source)

Day 1: Outdoor Unit & Electrical

What happens:

  • Outdoor heat pump unit delivered and positioned (wall-mounted or ground pad)
  • Drilling through wall for refrigerant pipes and cables
  • Electrician installs dedicated circuit and wiring
  • Condensate drain pipe installed

Your old boiler stays connected and working throughout.

Day 2: Indoor Unit & Pipework

  • Indoor heat pump unit installed (usually in garage, utility room, or where boiler was)
  • Hot water cylinder installed/connected if needed
  • Refrigerant pipes connected between indoor and outdoor units
  • System pipework connected to existing radiators
  • Buffer tank installed if required (depends on system design)

Day 3: Commissioning & Handover

  • System filled, pressurized, and leak-tested
  • Heat pump started up and commissioned
  • Settings optimized for your home (flow temp, heating schedules)
  • Full system demonstration and handover
  • Old boiler decommissioned and removed
  • MCS certificate issued

Ground Source Installation

Ground source takes longer due to ground loop installation:

Horizontal Trenches (5-7 days)

Days 1-3: Excavate trenches 1.5m deep across 100-200m² of garden. Lay ground loop pipes in slinky or straight runs. Backfill and restore lawn.

Days 4-5: Indoor heat pump installation and connection to ground loop.

Days 6-7: System fill, commissioning, handover.

Vertical Boreholes (7-10 days)

Days 1-4: Drilling rig arrives. Drill 1-3 boreholes 50-150m deep. Insert ground loop pipes and grout.

Days 5-7: Indoor unit installation, connection, and manifold setup.

Days 8-10: Pressure testing, commissioning, optimization, and handover.

What to Expect During Installation

Disruption Level

  • ✓ You can stay at home throughout
  • ✓ No heating/hot water for 4-8 hours max (usually Day 2)
  • ✓ Some dust and noise (drilling, pipe work)
  • ✓ 2-3 engineers on site each day
  • ✓ Ground source: Garden inaccessible for 3-5 days

After Installation

The first few weeks are a "settling in" period:

  • Week 1-2:Installer remotely monitors performance and tweaks settings for optimal efficiency.
  • Month 1-3:You learn how to use the system. Heat pumps work differently to boilers—leave them running low continuously rather than blasting on/off.
  • 6-12 months:First annual service (usually free). Performance check and minor adjustments.

Common Installation Issues (and Solutions)

Issue: House not heating to desired temperature
Solution: Flow temperature too low. Installer adjusts up by 5°C. Most common in first 2 weeks.
Issue: Outdoor unit too noisy
Solution: Check anti-vibration mounts installed correctly. Add acoustic fence if needed.
Issue: High electricity bills immediately
Solution: Usually due to heat-up mode (bringing house to temp from cold). Bills normalize after 2-4 weeks.

Your Checklist

Before Installation:
  • ☐ EPC up to date with insulation completed
  • ☐ BUS grant approved (redemption code received)
  • ☐ Clear access to indoor installation location
  • ☐ Outdoor unit location agreed and clear
  • ☐ Deposit paid, installation dates confirmed